Power factor surcharge or incentive on your bill

Applies to consumers above 25 HP (18.65 kW) connected load, on the energy charges.

₹
kW

Result

Results appear here as you type.

Get this checked by an engineer

Indicative only. Rules, tariffs and site conditions vary; SKE engineers confirm the exact figures for approvals and designs.

Formula and basis

Below 0.900: surcharge 0.1% of energy charges for each 0.001 below. 0.950 to 0.970: incentive 0.05% for each 0.001 above 0.950. Above 0.970: a further 0.1% for each 0.001. Below 0.70 the DISCOM can serve disconnection notices.

Tariff source: RERC Tariff for Supply of Electricity 2025 (order dated 3.10.2025), Rajasthan DISCOMs.