Battery storage (BESS)

Battery storage for peak shaving and demand charges

Rajasthan HT bills charge for billing demand: the higher of the recorded maximum demand and 75% of contract demand. Above 105% of contract demand an extra charge applies. A battery that supplies the short peaks lowers the recorded demand.

kVA
kVA
kVA
h
%
%
₹/kWh
kWh

Result

Results appear here as you type.

Get this checked by an engineer

Indicative only. Rules, tariffs and site conditions vary; SKE engineers confirm the exact figures for approvals and designs.

Formula and basis

Battery kW = (MD − target) × PF. Battery kWh = kW × hours ÷ (DoD × RTE). Billing demand = max(MD, 0.75 × CD). Saving = fall in billing demand × fixed charge + avoided excess-demand charge (extra % of fixed and energy charges equal to the % by which demand exceeds the contract demand, above 105%).

Tariff source: RERC Tariff for Supply of Electricity 2025 (order dated 3.10.2025), Rajasthan DISCOMs.

New Connection & Load Extension: how SKE helps

Questions

Is peak shaving with a battery worth it in Rajasthan?

It pays best where short, sharp peaks push demand above the contract demand and trigger the excess-demand charge, or where a battery lets you reduce the contract demand itself. A flat load with long peaks needs a large, costly battery.