  3. Estimated design demand and transformer size (TCOS 7.5)

Load, tariff and equipment

Estimated design demand and transformer size (TCOS 7.5)

Used by the DISCOM for technical sanction of colonies, group housing and building complexes (TCOS 2021, clause 7.5(i)). Enter the areas that apply; leave the rest at zero.

sq ft
sq ft
sq ft
sq ft
sq ft
sq ft
nos
sq ft
sq ft

Result

Results appear here as you type.

Get this checked by an engineer

Indicative only. Rules, tariffs and site conditions vary; SKE engineers confirm the exact figures for approvals and designs.

Formula and basis

Domestic plots 1 kW, flats 4 kW, EWS/LIG 2 kW, non-domestic plots 4 kW, non-domestic built and resorts 5 kW, farm houses 2 kW, all per 1000 sq ft. Resort and farm house open areas add 25% of the built load. Industrial: 10 kW up to 1000 sq ft plus 5 kW for each further 1000 sq ft or part. Common facilities add 5% and miscellaneous 2%. kVA = kW ÷ 0.90. Lines and transformers are designed for 10% above this. Above 50 kVA: 11 kV supply with a transformer at the applicant's cost.

Tariff source: RERC Tariff for Supply of Electricity 2025 (order dated 3.10.2025), Rajasthan DISCOMs.

New Connection & Load Extension: how SKE helps

Questions

Can the developer declare a higher demand?

Yes. Where the developer indicates a higher demand, the higher figure is used (TCOS 2021, note to clause 7.5(i)).

WhatsApp